Assessment Year | 1989 |
---|---|
Principal Product | MILK PRODUCTS & CHEESE |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
n/a
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Wyoming |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,758 | 451,055 |
kWh
|
$0.048 |
Natural Gas | $11,744 | 3,620 |
MMBtu
|
$3.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,074 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,520 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2626: Avoid frost formation on evaporators | $1,340 | $3,000 |
$1,070
22,274
kWh
|
- | $270 | |
02 | 2.7261: Install timers and/or thermostats | $290 | $300 |
$50
1,758
kWh
|
$240
-
MMBtu
|
- | |
03 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $300 | $100 |
$300
6,155
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $90 | $105 |
$90
1,758
kWh
|
- | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $390 | $330 |
$390
7,913
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $280 | - |
$280
5,862
kWh
|
- | - | |
07 | 2.2136: Install / repair insulation on steam lines | $214 | $350 | - |
$214
-
MMBtu
|
- | |
08 | 2.2164: Turn off steam tracing during mild weather | $170 | $200 | - |
$170
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $3,074 | $4,385 |
$2,180
45,720
kWh
|
$624
-
MMBtu
|
$270 | ||
TOTAL IMPLEMENTED | $1,520 | $1,035 |
$1,110
23,446
kWh
|
$410
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs