ITAC Assessment: CO0161
ITAC logo
ITAC Assessment: CO0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product MILK PRODUCTS & CHEESE
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area
n/a
Annual Production 10,000,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Wyoming

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,758 451,055
kWh
Natural Gas $11,744 3,620
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,074 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2626: Avoid frost formation on evaporators $1,340 $3,000 $1,070
22,274
kWh
- $270
02 2.7261: Install timers and/or thermostats $290 $300 $50
1,758
kWh
$240
-
MMBtu
-
03 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $300 $100 $300
6,155
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $90 $105 $90
1,758
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $390 $330 $390
7,913
kWh
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $280 - $280
5,862
kWh
- -
07 2.2136: Install / repair insulation on steam lines $214 $350 - $214
-
MMBtu
-
08 2.2164: Turn off steam tracing during mild weather $170 $200 - $170
-
MMBtu
-
TOTAL RECOMMENDED $3,074 $4,385 $2,180
45,720
kWh
$624
-
MMBtu
$270
TOTAL IMPLEMENTED $1,520 $1,035 $1,110
23,446
kWh
$410
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs