| Assessment Year | 1989 |
|---|---|
| Principal Product | CONCRETE PIPE |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 60,000
ton
|
| Production Hrs. Annual | 2,652
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $107,815 | 1,315,064 |
kWh
|
$0.082 |
| Natural Gas | $82,849 | 22,843 |
MMBtu
|
$3.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,772 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,772 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6124: Establish equipment maintenance schedule | $2,680 | $900 |
$2,680
32,825
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,420 | $500 |
$1,420
17,292
kWh
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $250 | $300 | - |
$250
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $800 | $200 |
$800
9,672
kWh
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $760 | $1,400 |
$760
9,379
kWh
|
- | |
| 06 | 2.7261: Install timers and/or thermostats | $429 | $600 |
$17
586
kWh
|
$412
-
MMBtu
|
|
| 07 | 2.8113: Purchase gas directly from a contract gas supplier | $11,600 | $6,700 | - |
$11,600
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $463 | $387 |
$463
5,569
kWh
|
- | |
| 09 | 2.8121: Apply for tax-free status for energy purchases | $1,370 | $250 |
$1,370
-
kWh
|
- | |
| TOTAL RECOMMENDED | $19,772 | $11,237 |
$7,510
75,323
kWh
|
$12,262
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,772 | $11,237 |
$7,510
75,323
kWh
|
$12,262
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs