| Assessment Year | 1989 |
|---|---|
| Principal Product | ANIMAL FEED |
| NAICS |
n/a
|
| SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
n/a
|
| Annual Production | 70,000
ton
|
| Production Hrs. Annual | 4,936
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,918 | 2,823,857 |
kWh
|
$0.047 |
| Natural Gas | $49,916 | 15,252 |
MMBtu
|
$3.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,005 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,803 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,650 | $500 | - |
$4,650
-
MMBtu
|
- | |
| 02 | 2.2441: Preheat boiler makeup water with waste process heat | $2,253 | $13,500 | - |
$2,253
-
MMBtu
|
- | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,856 | $1,500 |
$8,251
176,729
kWh
|
$(-2,395.0)
-
MMBtu
|
- | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $963 | - |
$1,463
-
kWh
|
- | $(-500.0) | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,949 | $5,481 |
$2,949
63,013
kWh
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $4,942 | $3,500 |
$4,942
105,510
kWh
|
- | - | |
| 07 | 2.2122: Install / repair insulation on condensate lines | $678 | $200 | - |
$678
-
MMBtu
|
- | |
| 08 | 2.7261: Install timers and/or thermostats | $500 | $450 |
$143
5,862
kWh
|
$357
-
MMBtu
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $214 | $267 |
$214
4,689
kWh
|
- | - | |
| TOTAL RECOMMENDED | $23,005 | $25,398 |
$17,962
355,803
kWh
|
$5,543
-
MMBtu
|
$(-500.0) | ||
| TOTAL IMPLEMENTED | $17,803 | $6,417 |
$15,013
292,790
kWh
|
$3,290
-
MMBtu
|
$(-500.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs