| Assessment Year | 1989 |
|---|---|
| Principal Product | CONCRETE CONDUIT & PIPE |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 35 |
| Plant Area |
n/a
|
| Annual Production | 50,000
ton
|
| Production Hrs. Annual | 2,840
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,697 | 878,957 |
kWh
|
$0.078 |
| Natural Gas | $25,570 | 6,791 |
MMBtu
|
$3.77 |
| LPG | $2,005 | 250 |
MMBtu
|
$8.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,762 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $2,801 | $1,700 | - |
$2,801
-
MMBtu
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $243 | $700 | - |
$243
-
MMBtu
|
- | |
| 03 | 2.2136: Install / repair insulation on steam lines | $1,074 | $850 | - |
$1,074
-
MMBtu
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $1,656 | $2,500 | - |
$1,756
-
MMBtu
|
$(-100.0) | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,520 | $250 |
$1,520
19,343
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $423 | $1,060 |
$423
5,569
kWh
|
- | - | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $200 | $200 | - |
$200
-
MMBtu
|
- | |
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $220 | $500 | - |
$220
-
MMBtu
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $166 | $211 |
$166
2,052
kWh
|
- | - | |
| TOTAL RECOMMENDED | $8,303 | $7,971 |
$2,109
26,964
kWh
|
$6,294
-
MMBtu
|
$(-100.0) | ||
| TOTAL IMPLEMENTED | $3,762 | $3,661 |
$1,686
21,395
kWh
|
$2,176
-
MMBtu
|
$(-100.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs