ITAC Assessment: CO0099
ITAC logo
ITAC Assessment: CO0099
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product PORK PRODUCTS
NAICS
n/a
SIC 2011: Meat Packing Plants
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 37,000,000
lb
Production Hrs. Annual 0
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,687 2,713,072
kWh
Natural Gas $85,082 21,771
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,814 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $2,958 $300 - $2,958
-
MMBtu
02 2.2135: Repair and eliminate steam leaks $805 $900 - $805
-
MMBtu
03 2.2447: Heat water with exhaust heat $9,892 $20,200 - $9,892
-
MMBtu
04 2.2425: Use flue gases to heat process or service water $1,768 $4,000 - $1,768
-
MMBtu
05 2.2136: Install / repair insulation on steam lines $2,151 $3,488 - $2,151
-
MMBtu
06 2.2511: Insulate bare equipment $467 $2,300 - $467
-
MMBtu
07 2.7261: Install timers and/or thermostats $622 $25 - $622
-
MMBtu
08 2.7229: Air condition only space necessary $766 $500 $766
13,775
kWh
-
09 2.4221: Install compressor air intakes in coolest locations $94 $200 $94
1,758
kWh
-
10 2.8121: Apply for tax-free status for energy purchases $7,224 $250 $7,224
-
kWh
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $1,067 $606 $1,067
19,343
kWh
-
TOTAL RECOMMENDED $27,814 $32,769 $9,151
34,876
kWh
$18,663
-
MMBtu
TOTAL IMPLEMENTED $13,760 $4,963 $7,224
-
kWh
$6,536
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs