Assessment Year | 1987 |
---|---|
Principal Product | BONELESS BEEF PRODUCTS |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
n/a
|
Annual Production | 85,000
pieces
|
Production Hrs. Annual | 4,550
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $229,184 | 5,569,754 |
kWh
|
$0.041 |
Natural Gas | $355,344 | 77,310 |
MMBtu
|
$4.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $116,712 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $110,162 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $84,858 | $27,000 | - |
$84,858
-
MMBtu
|
|
02 | 2.2121: Increase amount of condensate returned | $19,460 | $1,000 | - |
$19,460
-
MMBtu
|
|
03 | 2.2491: Use cooling air which cools hot work pieces for space heating | $3,467 | $500 | - |
$3,467
-
MMBtu
|
|
04 | 2.2136: Install / repair insulation on steam lines | $573 | $500 | - |
$573
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $2,502 | $950 | - |
$2,502
-
MMBtu
|
|
06 | 2.2135: Repair and eliminate steam leaks | $4,535 | $250 | - |
$4,535
-
MMBtu
|
|
07 | 2.2111: Install steam trap | $483 | $220 | - |
$483
-
MMBtu
|
|
08 | 2.4221: Install compressor air intakes in coolest locations | $253 | $300 |
$253
6,155
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $581 | - |
$581
14,068
kWh
|
- | |
TOTAL RECOMMENDED | $116,712 | $30,720 |
$834
20,223
kWh
|
$115,878
-
MMBtu
|
||
TOTAL IMPLEMENTED | $110,162 | $29,270 |
$253
6,155
kWh
|
$109,909
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs