Assessment Year | 1987 |
---|---|
Principal Product | BREADS AND BUNS |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $196,015 | 3,648,886 |
kWh
|
$0.054 |
Natural Gas | $171,526 | 42,478 |
MMBtu
|
$4.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $50,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,665 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $6,799 | $2,000 |
$6,799
-
kWh
|
- | |
02 | 2.3191: Use demand controller or load shedder | $7,490 | $600 |
$10,092
43,962
kWh
|
$(-2,602.0)
-
MMBtu
|
|
03 | 2.2711: Utilize outside air instead of conditioned air for drying | $8,099 | $12,000 | - |
$8,099
-
MMBtu
|
|
04 | 2.2121: Increase amount of condensate returned | $6,600 | $6,000 | - |
$6,600
-
MMBtu
|
|
05 | 2.2135: Repair and eliminate steam leaks | $2,860 | - | - |
$2,860
-
MMBtu
|
|
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,746 | $300 | - |
$1,746
-
MMBtu
|
|
07 | 2.1222: Install turbulators | $1,574 | $600 | - |
$1,574
-
MMBtu
|
|
08 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,137 | $200 |
$4,137
84,115
kWh
|
- | |
09 | 2.4221: Install compressor air intakes in coolest locations | $865 | $300 |
$865
17,585
kWh
|
- | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,169 | $100 |
$1,169
23,740
kWh
|
- | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,008 | $100 |
$1,008
20,516
kWh
|
- | |
12 | 2.4312: Improve lubrication practices | $3,325 | - |
$3,325
67,702
kWh
|
- | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,706 | $1,116 |
$4,706
95,838
kWh
|
- | |
TOTAL RECOMMENDED | $50,378 | $23,316 |
$32,101
353,458
kWh
|
$18,277
-
MMBtu
|
||
TOTAL IMPLEMENTED | $24,665 | $8,716 |
$11,885
241,794
kWh
|
$12,780
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs