Assessment Year | 1986 |
---|---|
Principal Product | PACKAGED MILK & COTTAGE CHEESE |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 21,000
Tgal
|
Production Hrs. Annual | 6,604
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $496,494 | 9,337,925 |
kWh
|
$0.053 |
Natural Gas | $132,698 | 31,992 |
MMBtu
|
$4.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $9,363 | $10,500 |
$9,363
-
kWh
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,439 | $300 | - |
$5,439
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,707 | $10,000 | - |
$7,707
-
MMBtu
|
|
04 | 2.2441: Preheat boiler makeup water with waste process heat | $14,637 | $10,000 | - |
$14,637
-
MMBtu
|
|
05 | 2.4312: Improve lubrication practices | $12,489 | - |
$12,489
235,053
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,024 | $700 |
$8,024
150,938
kWh
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,935 | $800 |
$1,935
36,342
kWh
|
- | |
08 | 2.7231: Use radiant heater for spot heating | $3,692 | $9,100 | - |
$3,692
-
MMBtu
|
|
09 | 2.4239: Eliminate or reduce compressed air usage | $7,606 | $12,000 |
$7,606
143,025
kWh
|
- | |
10 | 2.7492: Use proper thickness of insulation on building envelope | $366 | $892 | - |
$366
-
MMBtu
|
|
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,813 | $903 |
$1,813
33,998
kWh
|
- | |
TOTAL RECOMMENDED | $73,071 | $55,195 |
$41,230
599,356
kWh
|
$31,841
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs