ITAC Assessment: CO0062
ITAC logo
ITAC Assessment: CO0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product CORRUGATED BOXES
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 72
Plant Area
n/a
Annual Production 110,000
thousand feet
Production Hrs. Annual 4,030
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,557 922,919
kWh
Natural Gas $36,596 7,895
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,572

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,721 $40 - $1,721
-
MMBtu
02 2.7243: Improve air circulation with destratification fans / other methods $10,638 $9,200 $(-1,612.0)
(-20,223)
kWh
$12,250
-
MMBtu
03 2.7231: Use radiant heater for spot heating $7,549 $15,000 - $7,549
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,765 $3,300 $4,765
59,789
kWh
-
05 2.4312: Improve lubrication practices $3,995 - $3,995
50,117
kWh
-
06 2.2135: Repair and eliminate steam leaks $3,931 $200 - $3,931
-
MMBtu
07 2.7492: Use proper thickness of insulation on building envelope $1,953 $2,824 - $1,953
-
MMBtu
08 2.1222: Install turbulators $947 $750 - $947
-
MMBtu
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $934 $200 $934
11,723
kWh
-
10 2.4221: Install compressor air intakes in coolest locations $491 $300 $491
6,155
kWh
-
11 2.4231: Reduce the pressure of compressed air to the minimum required $584 $20 $584
7,327
kWh
-
12 2.7142: Utilize higher efficiency lamps and/or ballasts $1,862 $627 $1,862
23,447
kWh
-
TOTAL RECOMMENDED $39,370 $32,461 $11,019
138,335
kWh
$28,351
-
MMBtu
TOTAL IMPLEMENTED $23,572 $10,567 $5,670
71,219
kWh
$17,902
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs