| Assessment Year | 1985 |
|---|---|
| Principal Product | POLYURETHANE CASTER WHEELS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
n/a
|
| Annual Production | 300,000
lb
|
| Production Hrs. Annual | 2,444
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $47,847 | 793,083 |
kWh
|
$0.060 |
| Natural Gas | $10,117 | 2,108 |
MMBtu
|
$4.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,533 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,249 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $816 | $500 | - |
$816
-
MMBtu
|
|
| 02 | 2.7262: Separate controls of air handlers from ac/ heating systems | $816 | $2,000 |
$816
13,482
kWh
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $4,062 | $596 |
$1,210
19,930
kWh
|
$2,852
-
MMBtu
|
|
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $8,406 | - |
$13,727
227,433
kWh
|
$(-5,321.0)
-
MMBtu
|
|
| 05 | 2.3191: Use demand controller or load shedder | $2,972 | $3,600 |
$2,972
-
kWh
|
- | |
| 06 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $596 | $1,500 | - |
$596
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $865 | $1,500 |
$865
14,361
kWh
|
- | |
| TOTAL RECOMMENDED | $18,533 | $9,696 |
$19,590
275,206
kWh
|
$(-1,057.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,249 | $8,600 |
$4,653
27,843
kWh
|
$596
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs