| Assessment Year | 2013 | 
|---|---|
| Principal Product | Pressure sensitive tape and film | 
| NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing | 
| SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified | 
| Sales Range | $10 M  to 50M  | 
    
| # of Employees | 39 | 
| Plant Area | 
                            400,000
                 
ft2
 
                     | 
    
| Annual Production | 10,784
             
ton
 
         | 
    
| Production Hrs. Annual | 8,760
             
hrs
 
         | 
    
| Location (State) | Colorado | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $594,977 | 10,776,413 | 
             
kWh
 
         | 
        $0.055 | 
| Electricity Demand | $398,519 | 21,602 | 
             
kW-mo/yr
 
         | 
        $18.45 | 
| Electricity Fees | $2,655 | - | 
             | 
        - | 
| Natural Gas | $247,316 | 59,543 | 
             
MMBtu
 
         | 
        $4.15 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,790 | 
             See individual recommendations below 
            *Non-energy impacts included in savings.
         | 
    ||
| IMPLEMENTED SAVINGS* | $18,420 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | 
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,930 | $1,310 | 
                        $13,210
                                                     214,300
                                 
                                            
kWh
 
                             | 
                                                                                
                        $4,720
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $6,370 | $31,720 | - | - | 
                        $6,370
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                    |
| 03 | 2.2135: Repair and eliminate steam leaks | $490 | $230 | - | - | 
                        $490
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                    |
| TOTAL RECOMMENDED | $24,790 | $33,260 | 
                        $13,210
                                                     214,300
                                 
                                            
kWh
 
                             | 
                                                                                
                        $4,720
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                
                        $6,860
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                    ||
| TOTAL IMPLEMENTED | $18,420 | $1,540 | 
                        $13,210
                                                     214,300
                                 
                                            
kWh
 
                             | 
                                                                                
                        $4,720
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                
                        $490
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                    ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs