| Assessment Year | 2013 |
|---|---|
| Principal Product | Pressure sensitive tape and film |
| NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
| SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 39 |
| Plant Area |
400,000
ft2
|
| Annual Production | 10,784
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $594,977 | 10,776,413 |
kWh
|
$0.055 |
| Electricity Demand | $398,519 | 21,602 |
kW-mo/yr
|
$18.45 |
| Electricity Fees | $2,655 | - |
|
- |
| Natural Gas | $247,316 | 59,543 |
MMBtu
|
$4.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,420 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,930 | $1,310 |
$13,210
214,300
kWh
|
$4,720
-
kW-mo/yr
|
- | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $6,370 | $31,720 | - | - |
$6,370
-
MMBtu
|
|
| 03 | 2.2135: Repair and eliminate steam leaks | $490 | $230 | - | - |
$490
-
MMBtu
|
|
| TOTAL RECOMMENDED | $24,790 | $33,260 |
$13,210
214,300
kWh
|
$4,720
-
kW-mo/yr
|
$6,860
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $18,420 | $1,540 |
$13,210
214,300
kWh
|
$4,720
-
kW-mo/yr
|
$490
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs