| Assessment Year | 2025 |
|---|---|
| Principal Product | Bus maintenance facility |
| NAICS | 485111: Mixed Mode Transit Systems |
| SIC | 4111: Local and Suburban Transit |
| Sales Range | less than $500 k |
| # of Employees | 50 |
| Plant Area |
400,000
ft2
|
| Annual Production | 36,500
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $200,849 | 5,124,604 |
kWh
|
$0.039 | |
| Electricity Demand | $195,658 | 8,167 |
kW-mo/yr
|
$23.96 | |
| Electricity Fees | $15,788 | - |
|
- | |
| Natural Gas | $3,486 | 388 |
MMBtu
|
$9.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $81,910 | 7,800 |
Tgal
|
$10.50 | |
| TOTAL YEARLY COSTS | $497,692 | ||||
| RECOMMENDED SAVINGS* | $59,846 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,499 | $81,585 |
$9,780
249,533
kWh
|
$16,719
-
kW-mo/yr
|
- | - | |
| 02 | 2.9114: Use solar heat to make electricty | $14,804 | $82,205 |
$14,804
330,298
kWh
|
- | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $14,192 | $65,292 |
$8,824
88,160
kWh
|
$5,368
-
kW-mo/yr
|
- | - | |
| 04 | 3.4151: Minimize water usage | $3,382 | $10,387 | - | - | - |
$3,382
-
Tgal
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $524 | $4,942 |
$524
13,367
kWh
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $205 | $182 |
$112
2,846
kWh
|
$94
-
kW-mo/yr
|
- | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $239 | $200 | - | - |
$239
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $59,846 | $244,793 |
$34,044
684,203
kWh
|
$22,181
-
kW-mo/yr
|
$239
-
MMBtu
|
$3,382
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs