| Assessment Year | 2024 |
|---|---|
| Principal Product | Polybutadiene Resins |
| NAICS | 325212: Synthetic Rubber Manufacturing |
| SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
| Sales Range | $1 M to 5M |
| # of Employees | 30 |
| Plant Area |
35,566
ft2
|
| Annual Production | 1,825
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $63,494 | 1,325,059 |
kWh
|
$0.048 | |
| Electricity Demand | $47,445 | 2,462 |
kW-mo/yr
|
$19.27 | |
| Electricity Fees | $14,408 | - |
|
- | |
| Natural Gas | $85,150 | 12,945 |
MMBtu
|
$6.58 | |
| Waste Disposal Costs | |||||
| Water Usage | $19,472 | 2,096 |
Tgal
|
$9.29 | |
| TOTAL YEARLY COSTS | $229,969 | ||||
| RECOMMENDED SAVINGS* | $10,313 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2622: Replace existing chiller with high efficiency model | $4,303 | $55,212 |
$2,197
45,847
kWh
|
$743
-
kW-mo/yr
|
$1,363
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,289 | $11,963 |
$1,052
21,955
kWh
|
$1,237
-
kW-mo/yr
|
- | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $800 | $12,180 |
$235
4,894
kWh
|
$566
-
kW-mo/yr
|
- | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $204 | $796 |
$204
4,262
kWh
|
- | - | - | |
| 05 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $36 | $146 |
$6
119
kWh
|
- |
$30
-
MMBtu
|
- | |
| 06 | 2.2136: Install / repair insulation on steam lines | $155 | $428 | - | - |
$155
-
MMBtu
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,525 | $116 | - | - | - | $2,525 | |
| TOTAL RECOMMENDED | $10,313 | $80,841 |
$3,693
77,077
kWh
|
$2,546
-
kW-mo/yr
|
$1,549
-
MMBtu
|
$2,525 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs