| Assessment Year | 2024 |
|---|---|
| Principal Product | Hotel Services |
| NAICS | 721110: Hotels (except Casino Hotels) and Motels |
| SIC | 7011: Hotels and Motels |
| Sales Range | $10 M to 50M |
| # of Employees | 268 |
| Plant Area |
155,496
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $267,564 | 5,603,010 |
kWh
|
$0.048 | |
| Electricity Demand | $219,398 | 11,252 |
kW-mo/yr
|
$19.50 | |
| Electricity Fees | $102,186 | - |
|
- | |
| Natural Gas | $238,056 | 26,315 |
MMBtu
|
$9.05 | |
| Waste Disposal Costs | |||||
| Water Usage | $188,057 | 21,838 |
Tgal
|
$8.61 | |
| TOTAL YEARLY COSTS | $1,015,262 | ||||
| RECOMMENDED SAVINGS* | $81,111 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4113: Treat and reuse rinse waters | $80,106 | $200,135 | - | - | - |
$32,245
-
Tgal
|
$47,861
-
Tgal
|
|
| 02 | 2.2211: Use optimum temperature | $626 | - | - | - |
$626
-
MMBtu
|
- | - | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $171 | $149 |
$6
128
kWh
|
- |
$165
-
MMBtu
|
- | - | |
| 04 | 2.2694: Use highest temperature for chilling or cold storage | $92 | - |
$59
1,226
kWh
|
$33
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $79 | - |
$79
1,643
kWh
|
- | - | - | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $37 | $405 | - | - |
$37
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $81,111 | $200,689 |
$144
2,997
kWh
|
$33
-
kW-mo/yr
|
$828
-
MMBtu
|
$32,245
-
Tgal
|
$47,861
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs