ITAC Assessment: CM1029
ITAC logo
ITAC Assessment: CM1029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Bottle and soft drink manufacturing
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 170
Plant Area 250,000
ft2
Annual Production 20,000,000
units
Production Hrs. Annual 5,460
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $425,016 9,163,490
kWh
Electricity Demand $454,440 23,469
kW-mo/yr
Electricity Fees $88,563 -
Natural Gas $248,429 25,347
MMBtu
TOTAL YEARLY COSTS $1,216,447
RECOMMENDED SAVINGS* $223,032 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $86,254

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.6218: Turn off equipment when not in use $14,259 $23,838 $14,259
307,445
kWh
- - -
02 2.8226: Increase efficiency of trucks $113,963 $779,750 $9,963
214,812
kWh
- - $104,000
03 2.4221: Install compressor air intakes in coolest locations $8,556 $3,717 $5,530
119,182
kWh
$3,026
-
kW-mo/yr
- -
04 2.1224: Replace boiler $8,337 $38,130 - - $8,337
-
MMBtu
-
05 2.8121: Apply for tax-free status for energy purchases $76,117 $8,000 - - - $76,117
06 2.8114: Change rate schedules or other changes in utility service $1,800 - - - - $1,800
TOTAL RECOMMENDED $223,032 $853,435 $29,752
641,439
kWh
$3,026
-
kW-mo/yr
$8,337
-
MMBtu
$181,917
TOTAL IMPLEMENTED $86,254 $46,130 - - $8,337
-
MMBtu
$77,917
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs