Assessment Year | 2016 |
---|---|
Principal Product | Custom pressure vessels and custom fabrications |
NAICS | 332313: Plate Work Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
73,800
ft2
|
Annual Production | 100,000
units
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Wyoming |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,485 | 821,640 |
kWh
|
$0.038 |
Electricity Demand | $74,590 | 4,189 |
kW-mo/yr
|
$17.81 |
Electricity Fees | $876 | - |
|
- |
Natural Gas | $73,587 | 12,260 |
MMBtu
|
$6.00 |
TOTAL YEARLY COSTS | $180,538 | |||
RECOMMENDED SAVINGS* | $36,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,620 | $12,560 |
$220
5,700
kWh
|
$3,820
-
kW-mo/yr
|
$7,580
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,690 | $840 |
$1,360
34,900
kWh
|
$3,330
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,070 | $46,190 |
$5,480
141,200
kWh
|
$13,270
-
kW-mo/yr
|
- | $200 | $1,120 | |
TOTAL RECOMMENDED | $36,380 | $59,590 |
$7,060
181,800
kWh
|
$20,420
-
kW-mo/yr
|
$7,580
-
MMBtu
|
$200 | $1,120 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs