ITAC Assessment: CO0732
ITAC logo
ITAC Assessment: CO0732
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Custom pressure vessels and custom fabrications
NAICS 332313: Plate Work Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 43
Plant Area 73,800
ft2
Annual Production 100,000
units
Production Hrs. Annual 2,210
hrs
Location (State) Wyoming

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,485 821,640
kWh
Electricity Demand $74,590 4,189
kW-mo/yr
Electricity Fees $876 -
Natural Gas $73,587 12,260
MMBtu
TOTAL YEARLY COSTS $180,538
RECOMMENDED SAVINGS* $36,380 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,620 $12,560 $220
5,700
kWh
$3,820
-
kW-mo/yr
$7,580
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,690 $840 $1,360
34,900
kWh
$3,330
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $20,070 $46,190 $5,480
141,200
kWh
$13,270
-
kW-mo/yr
- $200 $1,120
TOTAL RECOMMENDED $36,380 $59,590 $7,060
181,800
kWh
$20,420
-
kW-mo/yr
$7,580
-
MMBtu
$200 $1,120
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs