| Assessment Year | 2021 |
|---|---|
| Principal Product | Railroad Products |
| NAICS | 336510: Railroad Rolling Stock Manufacturing |
| SIC | 3743: Railroad Equipment |
| Sales Range | $1 M to 5M |
| # of Employees | 58 |
| Plant Area |
161,000
ft2
|
| Annual Production | 32,000
units
|
| Production Hrs. Annual | 2,130
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $65,152 | 1,713,600 |
kWh
|
$0.038 | |
| Electricity Demand | $93,532 | 7,668 |
kW-mo/yr
|
$12.20 | |
| Electricity Fees | $9,912 | - |
|
- | |
| Natural Gas | $16,837 | 208,675 |
MMBtu
|
$0.081 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,586 | 129 |
Tgal
|
$12.31 | |
| Water Disposal | $1,198 | 129 |
Tgal
|
$9.30 | |
| TOTAL YEARLY COSTS | $188,217 | ||||
| RECOMMENDED SAVINGS* | $12,654 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,665 | $4,684 |
$3,518
87,960
kWh
|
$2,146
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $1,957 | $3,255 |
$1,957
48,930
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $512 | - |
$266
6,640
kWh
|
$246
-
kW-mo/yr
|
|
| 04 | 2.7261: Install timers and/or thermostats | $3,930 | - |
$3,930
98,253
kWh
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $590 | $2,100 |
$508
13,364
kWh
|
$82
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $12,654 | $10,039 |
$10,180
255,147
kWh
|
$2,475
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs