Assessment Year | 2021 |
---|---|
Principal Product | Automotive parts |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
10,994
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 6,672
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $420,232 | 3,688,160 |
kWh
|
$0.11 | |
Electricity Demand | $6,051 | 2,685 |
kW-mo/yr
|
$2.25 | |
Electricity Fees | $7,875 | - |
|
- | |
Natural Gas | $14,809 | 1,292 |
MMBtu
|
$11.46 | |
Waste Disposal Costs | |||||
Water Usage | $4,692 | 709 |
Tgal
|
$6.62 | |
Water Disposal | $7,308 | 709 |
Tgal
|
$10.31 | |
TOTAL YEARLY COSTS | $460,967 | ||||
RECOMMENDED SAVINGS* | $44,446 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $24,222 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,588 | $3,733 |
$11,190
98,212
kWh
|
$398
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $5,838 | $656 |
$5,838
51,241
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,376 | $1,720 |
$1,372
12,041
kWh
|
$4
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,257 | $43,750 |
$18,275
160,391
kWh
|
$982
-
kW-mo/yr
|
- | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $967 | $400 | - |
$967
-
kW-mo/yr
|
- | |
06 | 2.7442: Keep doors and windows shut when not on use | $797 | - |
$797
6,998
kWh
|
- | - | |
07 | 2.7221: Lower temperature during the winter season and vice-versa | $567 | - |
$567
4,979
kWh
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $4,055 | $2,500 | - | - |
$4,055
-
MMBtu
|
|
TOTAL RECOMMENDED | $44,446 | $52,759 |
$38,040
333,861
kWh
|
$2,351
-
kW-mo/yr
|
$4,055
-
MMBtu
|
||
TOTAL IMPLEMENTED | $24,222 | $8,609 |
$19,765
173,470
kWh
|
$402
-
kW-mo/yr
|
$4,055
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs