ITAC Assessment: CL2008
ITAC logo
ITAC Assessment: CL2008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Automotive, painted equipment
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 62,000
ft2
Annual Production 20,000,000
pieces
Production Hrs. Annual 5,500
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $147,384 1,387,285
kWh
Electricity Fees $6,955 -
Natural Gas $179,834 22,538
MMBtu
Waste Disposal Costs
Water Usage $9,615 2
Tgal
Water Disposal $9,615 2
Tgal
TOTAL YEARLY COSTS $353,403
RECOMMENDED SAVINGS* $7,534 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,625

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $3,868 - $3,868
36,405
kWh
-
02 2.2442: Preheat combustion air with waste heat $908 $4,500 - $908
-
MMBtu
03 2.7447: Install vinyl strip / high speed / air curtain doors $2,758 $2,616 - $2,758
-
MMBtu
TOTAL RECOMMENDED $7,534 $7,116 $3,868
36,405
kWh
$3,666
-
MMBtu
TOTAL IMPLEMENTED $6,625 $2,616 $3,868
36,405
kWh
$2,758
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs