| Assessment Year | 2026 |
|---|---|
| Principal Product | Hotel and Casino |
| NAICS | 721120: Casino Hotels |
| SIC | 7011: Hotels and Motels |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
100,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $274,410 | 2,137,006 |
kWh
|
$0.13 |
| Electricity Demand | $147,688 | 4,224 |
kW-mo/yr
|
$34.96 |
| Electricity Fees | $85,342 | - |
|
- |
| Natural Gas | $69,460 | 4,114 |
MMBtu
|
$16.88 |
| TOTAL YEARLY COSTS | $576,900 | |||
| RECOMMENDED SAVINGS* | $149,702 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1224: Replace boiler | $48,378 | $180,000 | - | - |
$48,378
-
MMBtu
|
|
| 02 | 2.4322: Use or replace with energy efficient substitutes | $29,228 | $150,000 |
$29,228
227,635
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,957 | $27,000 |
$18,431
143,550
kWh
|
$7,526
-
kW-mo/yr
|
- | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $16,463 | $43,000 |
$16,463
128,220
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,063 | $28,600 |
$11,700
91,104
kWh
|
$4,363
-
kW-mo/yr
|
- | |
| 06 | 2.7262: Separate controls of air handlers from ac/ heating systems | $10,135 | $1,600 |
$10,135
78,930
kWh
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $3,478 | $20,000 | - | - |
$3,478
-
MMBtu
|
|
| TOTAL RECOMMENDED | $149,702 | $450,200 |
$85,957
669,439
kWh
|
$11,889
-
kW-mo/yr
|
$51,856
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs