Assessment Year | 1993 |
---|---|
Principal Product | Rebuilt Engines |
NAICS |
n/a
|
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
144,000
ft2
|
Annual Production | 280,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $85,073 | 1,265,827 |
kWh
|
$0.067 |
Natural Gas | $71,061 | 15,064 |
MMBtu
|
$4.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,602 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,672 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $662 | - |
$662
20,809
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $133 | $452 | - |
$133
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,239 | $3,560 |
$3,239
29,601
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $829 | $546 |
$829
11,137
kWh
|
- | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,137 | - |
$1,137
16,706
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,418 | $10,680 |
$5,418
69,461
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $416 | $100 |
$416
11,723
kWh
|
- | |
08 | 2.1321: Replace fossil fuel equipment with electrical equipment | $743 | $880 | - |
$743
-
MMBtu
|
|
09 | 2.6218: Turn off equipment when not in use | $644 | - | - |
$644
-
MMBtu
|
|
10 | 2.3137: Use power during off-peak periods | $10,811 | - |
$10,811
-
kWh
|
- | |
11 | 2.8114: Change rate schedules or other changes in utility service | $16,570 | - |
$16,570
-
kWh
|
- | |
TOTAL RECOMMENDED | $40,602 | $16,218 |
$39,082
159,437
kWh
|
$1,520
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,672 | $15,666 |
$11,285
147,714
kWh
|
$1,387
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs