| Assessment Year | 2026 |
|---|---|
| Principal Product | Biotech Research and Development |
| NAICS | 541380: Testing Laboratories |
| SIC | 8734: Testing Laboratories |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
50,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,348 | 725,580 |
kWh
|
$0.18 |
| Electricity Demand | $39,497 | 2,485 |
kW-mo/yr
|
$15.89 |
| Electricity Fees | $21,238 | - |
|
- |
| TOTAL YEARLY COSTS | $192,083 | |||
| RECOMMENDED SAVINGS* | $158,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3141: Use battery storage for demand control | $86,252 | $793,800 |
$70,608
390,100
kWh
|
$15,644
-
kW-mo/yr
|
|
| 02 | 2.7262: Separate controls of air handlers from ac/ heating systems | $28,476 | $4,000 |
$28,476
157,325
kWh
|
- | |
| 03 | 2.7226: Use computer programs to optimize hvac performance | $18,338 | $1,165 |
$8,930
49,339
kWh
|
$9,408
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,959 | $4,100 |
$12,596
69,596
kWh
|
$1,363
-
kW-mo/yr
|
|
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $9,850 | $66,000 |
$9,850
54,423
kWh
|
- | |
| 06 | 2.7134: Use photocell controls | $2,113 | $1,725 |
$1,241
6,858
kWh
|
$872
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $158,988 | $870,790 |
$131,701
727,641
kWh
|
$27,287
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs