ITAC Assessment: CI0033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Auto Engine Components
NAICS 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing
SIC 3592: Carburetors, Pistons, Piston Rings, and Valves
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 71,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 6,783
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $456,538 5,500,721
kWh
Electricity Demand $246,438 11,099
kW-mo/yr
Electricity Fees $106,524 -
LPG $20,826 357
MMBtu
TOTAL YEARLY COSTS $830,326
RECOMMENDED SAVINGS* $182,959 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $104,681 $874,600 $78,574
946,680
kWh
$26,107
-
kW-mo/yr
- - -
02 2.2437: Recover waste heat from equipment $27,212 $6,000 $23,882
287,737
kWh
$3,330
-
kW-mo/yr
- - -
03 2.7232: Replace existing hvac unit with high efficiency model $18,262 $72,000 $18,262
220,029
kWh
- - - -
04 2.8227: Adjust / maintain fork lift trucks for most efficient operation $15,193 $60,000 $(-3,635.0)
(-43,800)
kWh
$(-1,998.0)
-
kW-mo/yr
$20,826
-
MMBtu
- -
05 2.7262: Separate controls of air handlers from ac/ heating systems $10,622 $800 $10,622
127,980
kWh
- - - -
06 2.7134: Use photocell controls $5,863 $5,400 $2,105
25,361
kWh
$3,155
-
kW-mo/yr
- $548 $55
07 2.4133: Use most efficient type of electric motors $1,126 $780 $831
10,013
kWh
$295
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $182,959 $1,019,580 $130,641
1,574,000
kWh
$30,889
-
kW-mo/yr
$20,826
-
MMBtu
$548 $55
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs