Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Wine
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $1
M
to 5
M
# of Employees 7
Plant Area 17,700
ft2
Annual Production 40,000
pieces
Production Hrs. Annual 1,530
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $167,714 1,150,394
kWh
Electricity Demand $26,515 1,251
kW-mo/yr
Electricity Fees $2,326 -
LPG $8,330 284
MMBtu
TOTAL YEARLY COSTS $204,885
RECOMMENDED SAVINGS* $90,470 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.9114: Use solar heat to make electricty $37,344 $306,517 $31,536
216,295
kWh
$5,808
-
kW-mo/yr
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $25,325 $20,000 $25,325
173,694
kWh
- -
03 2.3112: Store heated/ cooled water for use during peak demand periods $8,942 $30,000 - $8,942
-
kW-mo/yr
-
04 2.2622: Replace existing chiller with high efficiency model $8,940 $67,000 $8,940
61,320
kWh
- -
05 2.8227: Adjust / maintain fork lift trucks for most efficient operation $2,757 $20,000 $(-3,009.0)
(-20,639)
kWh
$(-2,564.0)
-
kW-mo/yr
$8,330
-
MMBtu
06 2.3132: Recharge batteries on during off-peak demand periods $2,563 $100 - $2,563
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $2,443 $1,800 $1,435
9,838
kWh
$1,008
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,321 $1,928 $776
5,321
kWh
$545
-
kW-mo/yr
-
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $835 $400 $574
3,937
kWh
$261
-
kW-mo/yr
-
TOTAL RECOMMENDED $90,470 $447,745 $65,577
449,766
kWh
$16,563
-
kW-mo/yr
$8,330
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs