| Assessment Year | 2024 |
|---|---|
| Principal Product | Academic Services |
| NAICS | 611110: Elementary and Secondary Schools |
| SIC | 8211: Elementary and Secondary Schools |
| Sales Range | $500 k to 1M |
| # of Employees | 120 |
| Plant Area |
30,000
ft2
|
| Annual Production | 800
units
|
| Production Hrs. Annual | 1,890
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $155,950 | 327,690 |
kWh
|
$0.48 | |
| Natural Gas | $11,487 | 492 |
MMBtu
|
$23.35 | |
| Other Gas | $828 | 492 |
MMBtu
|
$1.68 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,194 | 2,211 |
Tgal
|
$3.25 | |
| Water Disposal | $3,178 | 2,211 |
Tgal
|
$1.44 | |
| TOTAL YEARLY COSTS | $178,637 | ||||
| RECOMMENDED SAVINGS* | $203,730 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $117,628 | $341,230 |
$117,628
247,170
kWh
|
- | - | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $43,415 | $1,900 |
$43,415
91,226
kWh
|
- | - | |
| 03 | 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses | $14,256 | $92,800 |
$14,256
29,892
kWh
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $10,253 | $80,000 |
$10,253
21,546
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $5,668 | $5,200 |
$5,668
11,910
kWh
|
- | - | |
| 06 | 2.1321: Replace fossil fuel equipment with electrical equipment | $5,530 | $11,000 |
$5,530
11,619
kWh
|
- | - | |
| 07 | 3.4151: Minimize water usage | $5,321 | $22,000 | - | - |
$5,321
-
Tgal
|
|
| 08 | 2.1224: Replace boiler | $1,659 | $8,000 | - |
$1,659
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $203,730 | $562,130 |
$196,750
413,363
kWh
|
$1,659
-
MMBtu
|
$5,321
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs