ITAC Assessment: CI0028
ITAC logo
ITAC Assessment: CI0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Academic Services
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $500
k
to 1
M
# of Employees 120
Plant Area 30,000
ft2
Annual Production 800
units
Production Hrs. Annual 1,890
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $155,950 327,690
kWh
Natural Gas $11,487 492
MMBtu
Other Gas $828 492
MMBtu
Waste Disposal Costs
Water Usage $7,194 2,211
Tgal
Water Disposal $3,178 2,211
Tgal
TOTAL YEARLY COSTS $178,637
RECOMMENDED SAVINGS* $203,730 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings
01 2.9114: Use solar heat to make electricty $117,628 $341,230 $117,628
247,170
kWh
- -
02 2.6231: Utilize controls to operate equipment only when needed $43,415 $1,900 $43,415
91,226
kWh
- -
03 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $14,256 $92,800 $14,256
29,892
kWh
- -
04 2.7232: Replace existing hvac unit with high efficiency model $10,253 $80,000 $10,253
21,546
kWh
- -
05 2.7135: Install occupancy sensors $5,668 $5,200 $5,668
11,910
kWh
- -
06 2.1321: Replace fossil fuel equipment with electrical equipment $5,530 $11,000 $5,530
11,619
kWh
- -
07 3.4151: Minimize water usage $5,321 $22,000 - - $5,321
-
Tgal
08 2.1224: Replace boiler $1,659 $8,000 - $1,659
-
MMBtu
-
TOTAL RECOMMENDED $203,730 $562,130 $196,750
413,363
kWh
$1,659
-
MMBtu
$5,321
-
Tgal
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs