ITAC Assessment: CI0005
ITAC logo
ITAC Assessment: CI0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Metal Finishing
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 119
Plant Area 30,600
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 5,304
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $218,449 900,008
kWh
Electricity Demand $87,353 3,140
kW-mo/yr
Natural Gas $97,777 8,031
MMBtu
LPG $11,275 1,000
MMBtu
Waste Disposal Costs
Water Usage $49,420 8,094
Tgal
Water Disposal $2,229 8,094
Tgal
TOTAL YEARLY COSTS $466,503
RECOMMENDED SAVINGS* $82,270 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,046

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $38,200 $16,400 $38,200
157,344
kWh
- - -
02 2.1224: Replace boiler $15,803 $9,000 - - $15,803
-
MMBtu
-
03 2.8227: Adjust / maintain fork lift trucks for most efficient operation $9,639 $30,000 $(-1,636.0)
(-6,739)
kWh
- - $11,275
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,840 $300 $7,560
31,140
kWh
$1,280
-
kW-mo/yr
- -
05 2.9114: Use solar heat to make electricty $3,625 $13,372 $2,651
10,920
kWh
$974
-
kW-mo/yr
- -
06 2.3112: Store heated/ cooled water for use during peak demand periods $2,348 $8,100 - $2,348
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,483 $99 $1,174
4,896
kWh
$309
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,446 - $1,140
4,697
kWh
$306
-
kW-mo/yr
- -
09 2.6231: Utilize controls to operate equipment only when needed $563 $500 $563
2,317
kWh
- - -
10 2.3131: Reschedule plant operations or reduce load to avoid peaks $323 - - $323
-
kW-mo/yr
- -
TOTAL RECOMMENDED $82,270 $77,771 $49,652
204,575
kWh
$5,540
-
kW-mo/yr
$15,803
-
MMBtu
$11,275
-
MMBtu
TOTAL IMPLEMENTED $2,046 $599 $1,737
7,213
kWh
$309
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs