ITAC Assessment: CC0027
ITAC logo
ITAC Assessment: CC0027
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Portable Power Generation
NAICS 333120: Construction Machinery Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 499
Plant Area 441,650
ft2
Annual Production 33,000
units
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $700,279 13,263,227
kWh
Electricity Demand $146,958 32,157
kW-mo/yr
Electricity Fees $1,734 -
Natural Gas $364,772 33,700
MMBtu
Fuel Oil #2 $129,240 5,040
MMBtu
TOTAL YEARLY COSTS $1,342,983
RECOMMENDED SAVINGS* $85,450 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,444 $8,455 $2,444
46,113
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $860 $1,251 $769
14,506
kWh
$91
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,571 $25,000 $7,666
144,637
kWh
$905
-
kW-mo/yr
- -
04 2.2437: Recover waste heat from equipment $9,831 $10,000 $(-1,401.2)
(-26,438)
kWh
$(-204.6)
-
kW-mo/yr
$11,437
-
MMBtu
-
05 2.7442: Keep doors and windows shut when not on use $26,412 $80,000 - - $26,412
-
MMBtu
-
06 2.9114: Use solar heat to make electricty $7,831 $93,870 $7,831
147,764
kWh
- - -
07 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $91 $600 $91
1,713
kWh
- - -
08 2.3192: Use fossil fuel powered generator during peak demand periods $29,410 $782,250 $8,610
162,452
kWh
- - $20,800
TOTAL RECOMMENDED $85,450 $1,001,426 $26,010
490,747
kWh
$792
-
kW-mo/yr
$37,849
-
MMBtu
$20,800
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs