Assessment Year | 2023 |
---|---|
Principal Product | Bread |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
210,000
ft2
|
Annual Production | 60,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $510,843 | 9,407,520 |
kWh
|
$0.054 |
Electricity Demand | $145,329 | 12,129 |
kW-mo/yr
|
$11.98 |
Electricity Fees | $560 | - |
|
- |
Natural Gas | $391,268 | 46,677 |
MMBtu
|
$8.38 |
TOTAL YEARLY COSTS | $1,048,000 | |||
RECOMMENDED SAVINGS* | $132,060 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $38,944 | - |
$26,796
493,480
kWh
|
$12,148
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $18,525 | $10,000 |
$13,666
251,675
kWh
|
$4,859
-
kW-mo/yr
|
- | |
03 | 2.1212: Operate boilers on high fire setting | $4,544 | $10,000 | - | - |
$4,544
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,343 | $16,000 |
$12,343
227,321
kWh
|
- | - | |
05 | 2.2611: Moderate cooling tower outlet temperature | $3,233 | - |
$3,233
59,541
kWh
|
- | - | |
06 | 2.1392: Replace purchased steam with other energy source | $7,230 | $30,000 | - | - |
$7,230
-
MMBtu
|
|
07 | 2.2425: Use flue gases to heat process or service water | $47,241 | $125,000 | - | - |
$47,241
-
MMBtu
|
|
TOTAL RECOMMENDED | $132,060 | $191,000 |
$56,038
1,032,017
kWh
|
$17,007
-
kW-mo/yr
|
$59,015
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs