| Assessment Year | 2021 |
|---|---|
| Principal Product | Particle Board |
| NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
| SIC | 2499: Wood Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 140 |
| Plant Area |
2,064,163
ft2
|
| Annual Production | 130,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Montana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,382,504 | 49,784,668 |
kWh
|
$0.048 |
| Electricity Demand | $549,098 | 82,127 |
kW-mo/yr
|
$6.69 |
| Natural Gas | $1,721,267 | 473,100 |
MMBtu
|
$3.64 |
| TOTAL YEARLY COSTS | $4,652,868 | |||
| RECOMMENDED SAVINGS* | $73,489 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6124: Establish equipment maintenance schedule | $9,819 | $23 |
$8,247
171,811
kWh
|
$1,573
-
kW-mo/yr
|
|
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,317 | $313 |
$5,790
120,635
kWh
|
$1,527
-
kW-mo/yr
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $23,678 | $1,000 |
$19,987
402,960
kWh
|
$3,691
-
kW-mo/yr
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,150 | $13,435 |
$11,047
230,143
kWh
|
$2,103
-
kW-mo/yr
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,525 | $50 |
$16,396
341,586
kWh
|
$3,129
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $73,489 | $14,821 |
$61,467
1,267,135
kWh
|
$12,023
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs