| Assessment Year | 1984 |
|---|---|
| Principal Product | SHIPPING CONTAINERS |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $5 M to 10M |
| # of Employees | 57 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 3,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,337 | 980,950 |
kWh
|
$0.088 |
| Natural Gas | $83,416 | 14,541 |
MMBtu
|
$5.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $84,168 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $28,961 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $22,546 | $27,000 |
$22,551
236,811
kWh
|
$(-3,505.0)
-
MMBtu
|
$3,500 | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,320 | $3,000 |
$7,941
78,253
kWh
|
$379
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,013 | $670 |
$2,591
38,980
kWh
|
$(-578.0)
-
MMBtu
|
- | |
| 04 | 2.7492: Use proper thickness of insulation on building envelope | $18,628 | $99,000 | - |
$18,628
-
MMBtu
|
- | |
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $28,956 | $69,700 | - |
$28,956
-
MMBtu
|
- | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,705 | $3,000 | - |
$3,705
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $84,168 | $202,370 |
$33,083
354,044
kWh
|
$47,585
-
MMBtu
|
$3,500 | ||
| TOTAL IMPLEMENTED | $28,961 | $102,670 |
$10,532
117,233
kWh
|
$18,429
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs