ITAC Assessment: UD0116
ITAC logo
ITAC Assessment: UD0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product SHIPPING CONTAINERS
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 57
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 3,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,337 980,950
kWh
Natural Gas $83,416 14,541
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,168 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,961

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4322: Use or replace with energy efficient substitutes $22,546 $27,000 $22,551
236,811
kWh
$(-3,505.0)
-
MMBtu
$3,500
02 2.4231: Reduce the pressure of compressed air to the minimum required $8,320 $3,000 $7,941
78,253
kWh
$379
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,013 $670 $2,591
38,980
kWh
$(-578.0)
-
MMBtu
-
04 2.7492: Use proper thickness of insulation on building envelope $18,628 $99,000 - $18,628
-
MMBtu
-
05 2.7492: Use proper thickness of insulation on building envelope $28,956 $69,700 - $28,956
-
MMBtu
-
06 2.6212: Turn off equipment during breaks, reduce operating time $3,705 $3,000 - $3,705
-
MMBtu
-
TOTAL RECOMMENDED $84,168 $202,370 $33,083
354,044
kWh
$47,585
-
MMBtu
$3,500
TOTAL IMPLEMENTED $28,961 $102,670 $10,532
117,233
kWh
$18,429
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs