ITAC Assessment: BS0115
ITAC logo
ITAC Assessment: BS0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Concrete and Asphalt
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 5,219,050
ft2
Annual Production 200,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,384 2,635,220
kWh
Electricity Demand $112,537 19,631
kW-mo/yr
Natural Gas $262,132 49,899
MMBtu
TOTAL YEARLY COSTS $548,053
RECOMMENDED SAVINGS* $45,191 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,957 $11,662 $6,765
102,499
kWh
$1,192
-
kW-mo/yr
02 2.4221: Install compressor air intakes in coolest locations $481 $380 $360
5,460
kWh
$120
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,068 $280 $5,423
82,168
kWh
$645
-
kW-mo/yr
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $977 $350 $977
14,800
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,604 $144 $1,859
28,116
kWh
$745
-
kW-mo/yr
06 2.4231: Reduce the pressure of compressed air to the minimum required $3,334 $1,920 $2,835
42,956
kWh
$499
-
kW-mo/yr
07 2.4112: Install soft-start to eliminate nuisance trips $23,770 $8,000 - $23,770
-
kW-mo/yr
TOTAL RECOMMENDED $45,191 $22,736 $18,219
275,999
kWh
$26,972
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs