Assessment Year | 2004 |
---|---|
Principal Product | Newspaper pre-print production, Apparel manufacture |
NAICS | 315210: Cut and Sew Apparel Contractors |
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
166,000
ft2
|
Annual Production | 71,240,000
pieces
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $194,068 | 4,019,171 |
kWh
|
$0.048 |
Electricity Demand | $76,068 | 9,316 |
kW-mo/yr
|
$8.17 |
Electricity Fees | $34,463 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $97,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $4,659 | $600 | - | $4,659 | |
02 | 2.6218: Turn off equipment when not in use | $53,281 | $47,250 |
$53,281
1,072,934
kWh
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $1,440 | $610 |
$1,440
28,805
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,398 | $590 |
$7,398
148,938
kWh
|
- | |
05 | 2.4323: Use optimum size and capacity equipment | $1,667 | $5,660 |
$1,667
33,555
kWh
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,333 | $112 |
$3,333
67,110
kWh
|
- | |
07 | 2.7221: Lower temperature during the winter season and vice-versa | $25,291 | $6,163 |
$25,291
509,400
kWh
|
- | |
TOTAL RECOMMENDED | $97,069 | $60,985 |
$92,410
1,860,742
kWh
|
$4,659 | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs