ITAC Assessment: BS0109
ITAC logo
ITAC Assessment: BS0109
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 114,000
ft2
Annual Production 26,000
thousand feet
Production Hrs. Annual 5,720
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $579,678 12,208,022
kWh
Electricity Demand $201,031 29,688
kW-mo/yr
Electricity Fees $51,038 -
TOTAL YEARLY COSTS $831,747
RECOMMENDED SAVINGS* $95,274 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4221: Install compressor air intakes in coolest locations $9,601 $1,491 $7,394
155,727
kWh
$2,207
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $78,480 $10,867 $78,480
1,682,896
kWh
-
03 2.4322: Use or replace with energy efficient substitutes $6,902 $6,720 $6,902
145,359
kWh
-
04 2.7135: Install occupancy sensors $122 $39 $122
2,575
kWh
-
05 2.7224: Reduce space conditioning during non-working hours $169 $25 $169
3,549
kWh
-
TOTAL RECOMMENDED $95,274 $19,142 $93,067
1,990,106
kWh
$2,207
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs