| Assessment Year | 2017 |
|---|---|
| Principal Product | Trailers |
| NAICS | 336212: Truck Trailer Manufacturing |
| SIC | 3715: Truck Trailers |
| Sales Range | $5 M to 10M |
| # of Employees | 65 |
| Plant Area |
94,000
ft2
|
| Annual Production | 1,200
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $37,800 | 501,327 |
kWh
|
$0.075 | |
| Electricity Demand | $6,981 | 1,050 |
kW-mo/yr
|
$6.65 | |
| Electricity Fees | $1,856 | - |
|
- | |
| Natural Gas | $33,799 | 5,201 |
MMBtu
|
$6.50 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,148 | 335 |
Tgal
|
$3.43 | |
| Other Liquid (haz) | $6,177 | 2,656 |
gal
|
$2.33 | |
| TOTAL YEARLY COSTS | $87,761 | ||||
| RECOMMENDED SAVINGS* | $17,416 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $15,140 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $7,306 | $495 |
$7,306
95,586
kWh
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,159 | $10,362 |
$2,756
36,546
kWh
|
$1,403
-
kW-mo/yr
|
- | - | |
| 03 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $1,991 | $1,301 | - | - |
$1,991
-
MMBtu
|
- | |
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $194 | $682 |
$194
2,571
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,365 | $734 |
$1,655
21,831
kWh
|
$710
-
kW-mo/yr
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $436 | $672 |
$436
5,776
kWh
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $91 | $85 |
$91
1,211
kWh
|
- | - | - | |
| 08 | 2.8123: Pay utility bills on time | $874 | $144 | - | - | - | $874 | |
| TOTAL RECOMMENDED | $17,416 | $14,475 |
$12,438
163,521
kWh
|
$2,113
-
kW-mo/yr
|
$1,991
-
MMBtu
|
$874 | ||
| TOTAL IMPLEMENTED | $15,140 | $12,407 |
$12,153
159,739
kWh
|
$2,113
-
kW-mo/yr
|
- | $874 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs