Assessment Year | 2017 |
---|---|
Principal Product | Lumber and Other Building Materials |
NAICS | 321912: Cut Stock, Resawing Lumber, and Planing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
7,800
ft2
|
Annual Production | 135,000
thousand feet
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $706,357 | 21,430,450 |
kWh
|
$0.033 |
Electricity Demand | $171,817 | 43,304 |
kW-mo/yr
|
$3.97 |
Electricity Fees | $159,994 | - |
|
- |
TOTAL YEARLY COSTS | $1,038,168 | |||
RECOMMENDED SAVINGS* | $62,279 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,063 | $41,435 |
$9,331
282,761
kWh
|
$1,732
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $6,143 | $525 |
$4,168
126,306
kWh
|
$1,975
-
kW-mo/yr
|
- | |
03 | 2.3212: Optimize plant power factor | $10,844 | $25,166 | - | - | $10,844 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,138 | $1,400 |
$2,694
81,643
kWh
|
$444
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $261 | $660 |
$261
7,779
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $30,830 | $20,375 |
$18,271
553,646
kWh
|
$12,559
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $62,279 | $89,561 |
$34,725
1,052,135
kWh
|
$16,710
-
kW-mo/yr
|
$10,844 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs