ITAC Assessment: BS0101
ITAC logo
ITAC Assessment: BS0101
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Lumber and Other Building Materials
NAICS 321912: Cut Stock, Resawing Lumber, and Planing
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 7,800
ft2
Annual Production 135,000
thousand feet
Production Hrs. Annual 4,420
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $706,357 21,430,450
kWh
Electricity Demand $171,817 43,304
kW-mo/yr
Electricity Fees $159,994 -
TOTAL YEARLY COSTS $1,038,168
RECOMMENDED SAVINGS* $62,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,063 $41,435 $9,331
282,761
kWh
$1,732
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $6,143 $525 $4,168
126,306
kWh
$1,975
-
kW-mo/yr
-
03 2.3212: Optimize plant power factor $10,844 $25,166 - - $10,844
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,138 $1,400 $2,694
81,643
kWh
$444
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $261 $660 $261
7,779
kWh
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $30,830 $20,375 $18,271
553,646
kWh
$12,559
-
kW-mo/yr
-
TOTAL RECOMMENDED $62,279 $89,561 $34,725
1,052,135
kWh
$16,710
-
kW-mo/yr
$10,844
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs