Assessment Year | 2017 |
---|---|
Principal Product | Beer |
NAICS | 312120: Breweries |
SIC | 2082: Malt Beverages |
Sales Range | $1 M to 5M |
# of Employees | 86 |
Plant Area |
30,000
ft2
|
Annual Production | 310
Tgal
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $39,116 | 663,161 |
kWh
|
$0.059 | |
Electricity Demand | $11,799 | 2,542 |
kW-mo/yr
|
$4.64 | |
Electricity Fees | $607 | - |
|
- | |
Natural Gas | $38,494 | 5,667 |
MMBtu
|
$6.79 | |
Waste Disposal Costs | |||||
Water Usage | $8,034 | 2,433 |
Tgal
|
$3.30 | |
Water Disposal | $10,205 | 1,477 |
Tgal
|
$6.91 | |
Gaseous Waste | $13,657 | 55,650 |
lb
|
$0.25 | |
TOTAL YEARLY COSTS | $121,912 | ||||
RECOMMENDED SAVINGS* | $94,181 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Gaseous Waste Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5311: Recover and reuse waste material | $83,061 | $200,000 |
$(-104.0)
(-1,755)
kWh
|
$(-835.0)
-
kW-mo/yr
|
- | - | - | - | $84,000 | |
02 | 4.212: Adopt in-house material generation | $7,623 | $60,000 | - | - | - | - | - |
$7,623
-
lb
|
- | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $866 | $2,440 | - | - |
$866
-
MMBtu
|
- | - | - | - | |
04 | 2.1113: Reduce combustion air flow to optimum | $789 | $144 | - | - |
$789
-
MMBtu
|
- | - | - | - | |
05 | 3.4113: Treat and reuse rinse waters | $773 | $7,514 | - | - | - |
$201
-
Tgal
|
$572
-
Tgal
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $456 | $7 |
$456
7,734
kWh
|
- | - | - | - | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $428 | $308 |
$294
4,992
kWh
|
$134
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7224: Reduce space conditioning during non-working hours | $135 | $13 | - | - |
$135
-
MMBtu
|
- | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $50 | $260 |
$50
839
kWh
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $94,181 | $270,686 |
$696
11,810
kWh
|
$(-701.0)
-
kW-mo/yr
|
$1,790
-
MMBtu
|
$201
-
Tgal
|
$572
-
Tgal
|
$7,623
-
lb
|
$84,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Gaseous Waste Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs