ITAC Assessment: MA0477
ITAC logo
ITAC Assessment: MA0477
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Surgical Tape
NAICS
n/a
SIC 2835: In Vitro and In Vivo Diagnostic Substances
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 81,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,032
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $588,126 10,644,197
kWh
Electricity Demand $256,967 20,015
kW-mo/yr
Electricity Fees $2,845 -
Natural Gas $191,538 33,698
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,280 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2625: Chill water to the highest temperature possible $22,890 $2,000 $22,890
489,449
kWh
- -
02 2.2437: Recover waste heat from equipment $21,290 $103,000 $(-6,260.0)
(-133,939)
kWh
- $27,550
-
MMBtu
03 2.2614: Use cooling tower or economizer to replace chiller cooling $6,580 $21,000 $3,320
79,132
kWh
$3,260
-
kW-mo/yr
-
04 2.7224: Reduce space conditioning during non-working hours $3,910 - $570
13,189
kWh
$3,340
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,200 $11,700 $3,200
67,409
kWh
- -
06 2.7135: Install occupancy sensors $410 $500 $410
7,620
kWh
- -
TOTAL RECOMMENDED $58,280 $138,200 $24,130
522,860
kWh
$6,600
-
kW-mo/yr
$27,550
-
MMBtu
TOTAL IMPLEMENTED $3,610 $12,200 $3,610
75,029
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs