| Assessment Year | 2000 |
|---|---|
| Principal Product | Surgical Tape |
| NAICS |
n/a
|
| SIC | 2835: In Vitro and In Vivo Diagnostic Substances |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
81,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,032
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $588,126 | 10,644,197 |
kWh
|
$0.055 |
| Electricity Demand | $256,967 | 20,015 |
kW-mo/yr
|
$12.84 |
| Electricity Fees | $2,845 | - |
|
- |
| Natural Gas | $191,538 | 33,698 |
MMBtu
|
$5.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,280 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,610 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2625: Chill water to the highest temperature possible | $22,890 | $2,000 |
$22,890
489,449
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $21,290 | $103,000 |
$(-6,260.0)
(-133,939)
kWh
|
- |
$27,550
-
MMBtu
|
|
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,580 | $21,000 |
$3,320
79,132
kWh
|
$3,260
-
kW-mo/yr
|
- | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $3,910 | - |
$570
13,189
kWh
|
$3,340
-
kW-mo/yr
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,200 | $11,700 |
$3,200
67,409
kWh
|
- | - | |
| 06 | 2.7135: Install occupancy sensors | $410 | $500 |
$410
7,620
kWh
|
- | - | |
| TOTAL RECOMMENDED | $58,280 | $138,200 |
$24,130
522,860
kWh
|
$6,600
-
kW-mo/yr
|
$27,550
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,610 | $12,200 |
$3,610
75,029
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs