ITAC Assessment: BS0096
ITAC logo
ITAC Assessment: BS0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Fabricated Structural Metal
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 55,000
ft2
Annual Production 120
units
Production Hrs. Annual 5,304
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,465 1,204,164
kWh
Electricity Demand $41,452 4,914
kW-mo/yr
Natural Gas $29,024 3,738
MMBtu
TOTAL YEARLY COSTS $157,941
RECOMMENDED SAVINGS* $5,648 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,341

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,641 $1,104 $1,161
15,912
kWh
- - $480
02 2.4221: Install compressor air intakes in coolest locations $609 $175 $480
6,577
kWh
$129
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $355 $412 $355
4,862
kWh
- - -
04 2.7124: Make a practice of turning off lights when not needed $152 $15 $152
2,080
kWh
- - -
05 2.4226: Use / purchase optimum sized compressor $1,155 $430 $1,155
15,820
kWh
- - -
06 2.4112: Install soft-start to eliminate nuisance trips $1,509 $6,000 - $1,509
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $227 $564 $236
3,235
kWh
$62
-
kW-mo/yr
$(-71.0) -
TOTAL RECOMMENDED $5,648 $8,700 $3,539
48,486
kWh
$1,700
-
kW-mo/yr
$(-71.0) $480
TOTAL IMPLEMENTED $4,341 $8,255 $2,232
30,586
kWh
$1,700
-
kW-mo/yr
$(-71.0) $480
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs