| Assessment Year | 2017 |
|---|---|
| Principal Product | Fabricated Structural Metal |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
55,000
ft2
|
| Annual Production | 120
units
|
| Production Hrs. Annual | 5,304
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $87,465 | 1,204,164 |
kWh
|
$0.073 |
| Electricity Demand | $41,452 | 4,914 |
kW-mo/yr
|
$8.44 |
| Natural Gas | $29,024 | 3,738 |
MMBtu
|
$7.76 |
| TOTAL YEARLY COSTS | $157,941 | |||
| RECOMMENDED SAVINGS* | $5,648 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,341 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,641 | $1,104 |
$1,161
15,912
kWh
|
- | - | $480 | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $609 | $175 |
$480
6,577
kWh
|
$129
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $355 | $412 |
$355
4,862
kWh
|
- | - | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $152 | $15 |
$152
2,080
kWh
|
- | - | - | |
| 05 | 2.4226: Use / purchase optimum sized compressor | $1,155 | $430 |
$1,155
15,820
kWh
|
- | - | - | |
| 06 | 2.4112: Install soft-start to eliminate nuisance trips | $1,509 | $6,000 | - |
$1,509
-
kW-mo/yr
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $227 | $564 |
$236
3,235
kWh
|
$62
-
kW-mo/yr
|
$(-71.0) | - | |
| TOTAL RECOMMENDED | $5,648 | $8,700 |
$3,539
48,486
kWh
|
$1,700
-
kW-mo/yr
|
$(-71.0) | $480 | ||
| TOTAL IMPLEMENTED | $4,341 | $8,255 |
$2,232
30,586
kWh
|
$1,700
-
kW-mo/yr
|
$(-71.0) | $480 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs