| Assessment Year | 2017 |
|---|---|
| Principal Product | Trailers |
| NAICS | 336212: Truck Trailer Manufacturing |
| SIC | 3715: Truck Trailers |
| Sales Range | $100 M to 500M |
| # of Employees | 305 |
| Plant Area |
200,000
ft2
|
| Annual Production | 1,500
pieces
|
| Production Hrs. Annual | 4,020
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $133,298 | 2,739,363 |
kWh
|
$0.049 |
| Electricity Demand | $66,159 | 10,208 |
kW-mo/yr
|
$6.48 |
| Electricity Fees | $18,655 | - |
|
- |
| Natural Gas | $52,857 | 7,699 |
MMBtu
|
$6.87 |
| TOTAL YEARLY COSTS | $270,969 | |||
| RECOMMENDED SAVINGS* | $55,989 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,961 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $9,634 | $1,202 |
$9,634
197,977
kWh
|
- | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $4,164 | $45,960 |
$2,784
57,199
kWh
|
$1,380
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,935 | $15,234 |
$4,555
93,599
kWh
|
$1,380
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $9,156 | $20,491 | - | - | $9,156 | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $5,362 | $1,171 |
$3,880
79,666
kWh
|
$1,482
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,327 | $128 |
$1,290
26,489
kWh
|
$37
-
kW-mo/yr
|
- | - | |
| 07 | 2.4224: Upgrade controls on compressors | $9,891 | $13,498 |
$6,858
147,166
kWh
|
$3,033
-
kW-mo/yr
|
- | - | |
| 08 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $10,520 | $21,040 | - | - | - |
$10,520
-
MMBtu
|
|
| TOTAL RECOMMENDED | $55,989 | $118,724 |
$29,001
602,096
kWh
|
$7,312
-
kW-mo/yr
|
$9,156 |
$10,520
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,961 | $1,330 |
$10,924
224,466
kWh
|
$37
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs