| Assessment Year | 2017 |
|---|---|
| Principal Product | Sheet Metal |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $5 M to 10M |
| # of Employees | 36 |
| Plant Area |
23,000
ft2
|
| Annual Production | 1,100,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $44,008 | 764,186 |
kWh
|
$0.058 |
| Electricity Demand | $12,801 | 2,732 |
kW-mo/yr
|
$4.69 |
| Electricity Fees | $631 | - |
|
- |
| Natural Gas | $12,377 | 1,732 |
MMBtu
|
$7.15 |
| LPG | $5,100 | 199 |
MMBtu
|
$25.59 |
| TOTAL YEARLY COSTS | $74,918 | |||
| RECOMMENDED SAVINGS* | $3,280 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $1,874 | $500 | - | - |
$1,874
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $999 | $4,977 |
$985
17,100
kWh
|
$14
-
kW-mo/yr
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $146 | $30 |
$146
2,526
kWh
|
- | - | |
| 04 | 2.7241: Install outside air damper / economizer on hvac unit | $58 | $590 |
$58
1,000
kWh
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $203 | $628 |
$147
2,545
kWh
|
$56
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $3,280 | $6,725 |
$1,336
23,171
kWh
|
$70
-
kW-mo/yr
|
$1,874
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs