Assessment Year | 2016 |
---|---|
Principal Product | Wastewater Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 21 |
Plant Area |
472,000
ft2
|
Annual Production | 10,220,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Alaska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $331,582 | 3,536,800 |
kWh
|
$0.094 |
Electricity Demand | $94,821 | 5,408 |
kW-mo/yr
|
$17.53 |
Electricity Fees | $1,554 | - |
|
- |
Natural Gas | $606,834 | 72,296 |
MMBtu
|
$8.39 |
TOTAL YEARLY COSTS | $1,034,791 | |||
RECOMMENDED SAVINGS* | $111,304 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3322: Use existing dam to generate electricity | $84,096 | $646,400 |
$84,096
897,024
kWh
|
- | - | |
02 | 2.2511: Insulate bare equipment | $12,593 | $2,530 | - | - |
$12,593
-
MMBtu
|
|
03 | 2.1113: Reduce combustion air flow to optimum | $1,842 | $464 | - | - |
$1,842
-
MMBtu
|
|
04 | 2.1213: Direct warmest air to combustion intake | $4,190 | $6,640 | - | - |
$4,190
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,692 | $3,161 |
$3,745
39,946
kWh
|
$947
-
kW-mo/yr
|
- | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $3,891 | $3,900 |
$3,891
41,499
kWh
|
- | - | |
TOTAL RECOMMENDED | $111,304 | $663,095 |
$91,732
978,469
kWh
|
$947
-
kW-mo/yr
|
$18,625
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs