ITAC Assessment: BS0074
ITAC logo
ITAC Assessment: BS0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Liquid Animal Supplements
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 21
Plant Area 24,000
ft2
Annual Production 73,800
ton
Production Hrs. Annual 5,330
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,512 649,101
kWh
Electricity Demand $10,339 2,237
kW-mo/yr
Electricity Fees $608 -
Natural Gas $29,524 4,034
MMBtu
Fuel Oil #2 $144,072 9,690
MMBtu
TOTAL YEARLY COSTS $222,055
RECOMMENDED SAVINGS* $6,806 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,896

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $249 $117 $249
4,315
kWh
- -
02 2.4221: Install compressor air intakes in coolest locations $283 $448 $283
4,905
kWh
- -
03 2.1224: Replace boiler $2,331 $14,391 - - $2,331
-
MMBtu
04 2.2113: Repair or replace steam traps $2,326 $5,073 - - $2,326
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $111 $343 $97
1,683
kWh
$14
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $600 $2,800 $478
8,263
kWh
$122
-
kW-mo/yr
-
07 2.7224: Reduce space conditioning during non-working hours $199 $14 $29
510
kWh
- $170
-
MMBtu
08 2.4231: Reduce the pressure of compressed air to the minimum required $530 $7 $530
9,182
kWh
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $177 $483 $177
3,068
kWh
- -
TOTAL RECOMMENDED $6,806 $23,676 $1,843
31,926
kWh
$136
-
kW-mo/yr
$4,827
-
MMBtu
TOTAL IMPLEMENTED $5,896 $20,519 $1,239
21,470
kWh
- $4,657
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs