| Assessment Year | 2015 |
|---|---|
| Principal Product | Concrete Masonry Units |
| NAICS | 327331: Concrete Block and Brick Manufacturing |
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 29 |
| Plant Area |
65,000
ft2
|
| Annual Production | 548,000
pieces
|
| Production Hrs. Annual | 2,720
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $50,614 | 941,000 |
kWh
|
$0.054 |
| Electricity Demand | $24,113 | 4,130 |
kW-mo/yr
|
$5.84 |
| Electricity Fees | $202 | - |
|
- |
| Natural Gas | $56,338 | 7,644 |
MMBtu
|
$7.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,681 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,792 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,694 | $503 |
$34
625
kWh
|
$1,660
-
MMBtu
|
|
| 02 | 2.2437: Recover waste heat from equipment | $5,555 | $6,149 | - |
$5,555
-
MMBtu
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $98 | $200 |
$98
1,814
kWh
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,050 | $1,378 |
$1,050
19,516
kWh
|
- | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $1,284 | $2,208 |
$1,284
23,872
kWh
|
- | |
| TOTAL RECOMMENDED | $9,681 | $10,438 |
$2,466
45,827
kWh
|
$7,215
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,792 | $703 |
$132
2,439
kWh
|
$1,660
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs