ITAC Assessment: BS0060
ITAC logo
ITAC Assessment: BS0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Industrial Gases
NAICS 325120: Industrial Gas Manufacturing
SIC 2813: Industrial Gases
Sales Range $10
M
to 50
M
# of Employees 7
Plant Area 9,906
ft2
Annual Production 11,061
Tgal
Production Hrs. Annual 8,640
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,307,046 27,970,187
kWh
Electricity Demand $250,926 41,822
kW-mo/yr
Electricity Fees $3,785 -
Natural Gas $1,415 184
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,810 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $294

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $674 $1,555 $573
12,264
kWh
$101
-
kW-mo/yr
- -
02 2.3212: Optimize plant power factor $8,556 $17,382 - - $8,556 -
03 2.7135: Install occupancy sensors $294 $272 $294
6,281
kWh
- - -
04 2.2437: Recover waste heat from equipment $1,359 $2,116 - - - $1,359
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $479 $156 $479
10,259
kWh
- - -
06 2.4224: Upgrade controls on compressors $8,893 $26,927 $8,893
190,305
kWh
- - -
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $11,499 $5,813 $30,282
648,000
kWh
$450
-
kW-mo/yr
- $(-19,233.0)
-
MMBtu
08 3.1191: Change procedures / equipment / operating conditions $6,056 $1,870 $6,056
129,600
kWh
- - -
TOTAL RECOMMENDED $37,810 $56,091 $46,577
996,709
kWh
$551
-
kW-mo/yr
$8,556 $(-17,874.0)
-
MMBtu
TOTAL IMPLEMENTED $294 $272 $294
6,281
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs