ITAC Assessment: BS0052
ITAC logo
ITAC Assessment: BS0052
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Modular Buildings
NAICS 321992: Prefabricated Wood Building Manufacturing
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $50
M
to 100
M
# of Employees 355
Plant Area 160,000
ft2
Annual Production 1,215
units
Production Hrs. Annual 4,050
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,413 1,564,471
kWh
Electricity Demand $29,121 5,328
kW-mo/yr
Electricity Fees $974 -
Natural Gas $87,465 12,129
MMBtu
LPG $32,661 1,642
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,234 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings LPG Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $25,881 $3,501 $21,169
387,720
kWh
$4,712
-
kW-mo/yr
- - -
02 2.4224: Upgrade controls on compressors $3,691 $5,780 $3,691
67,608
kWh
- - - -
03 2.7224: Reduce space conditioning during non-working hours $16,954 $40 - - - $16,954
-
MMBtu
-
04 2.7492: Use proper thickness of insulation on building envelope $12,564 $13,200 - - - $12,564
-
MMBtu
-
05 2.7492: Use proper thickness of insulation on building envelope $1,687 $3,800 - - - $1,687
-
MMBtu
-
06 2.7231: Use radiant heater for spot heating $3,310 $7,200 $(-12,265.0)
(-224,640)
kWh
- - - $15,575
-
MMBtu
07 2.8112: Combine utility meters $810 $1,587 - - $810 - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,103 $17,841 $866
15,856
kWh
$237
-
kW-mo/yr
- - -
09 2.7135: Install occupancy sensors $48 $92 $48
884
kWh
- - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $185 $104 $143
2,623
kWh
$42
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $66,234 $53,145 $13,652
250,051
kWh
$4,992
-
kW-mo/yr
$810 $31,205
-
MMBtu
$15,575
-
MMBtu
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs