ITAC Assessment: GT0937
ITAC logo
ITAC Assessment: GT0937
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product large seam pipes
NAICS 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 640,000
ft2
Annual Production 38,769
units
Production Hrs. Annual 3,648
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $638,133 6,124,631
kWh
Natural Gas $292,787 49,679
MMBtu
TOTAL YEARLY COSTS $930,920
RECOMMENDED SAVINGS* $65,037 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $1,362 $310 $1,362
13,097
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,545 $4,311 $2,545
24,474
kWh
- -
03 2.3212: Optimize plant power factor $10,618 $38,920 - $10,618 -
04 2.2437: Recover waste heat from equipment $32,772 $100,000 - - $32,772
-
MMBtu
05 2.9114: Use solar heat to make electricty $17,740 $158,500 $17,740
170,261
kWh
- -
TOTAL RECOMMENDED $65,037 $302,041 $21,647
207,832
kWh
$10,618 $32,772
-
MMBtu
TOTAL IMPLEMENTED $3,907 $4,621 $3,907
37,571
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs