| Assessment Year | 2013 |
|---|---|
| Principal Product | Construction Equipment |
| NAICS | 333120: Construction Machinery Manufacturing |
| SIC | 3531: Construction Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
140,000
ft2
|
| Annual Production | 225,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $56,307 | 1,383,920 |
kWh
|
$0.041 |
| Electricity Demand | $26,466 | 4,621 |
kW-mo/yr
|
$5.73 |
| Electricity Fees | $10,352 | - |
|
- |
| Natural Gas | $68,498 | 9,893 |
MMBtu
|
$6.92 |
| Fuel Oil #2 | $664 | 17 |
MMBtu
|
$38.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,961 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $5,378 | $1,732 |
$5,378
132,186
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,556 | $523 |
$1,556
38,251
kWh
|
- | - | - | - | |
| 03 | 2.2447: Heat water with exhaust heat | $7,448 | $7,432 |
$(-265.6)
(-6,528)
kWh
|
$(-224.1)
-
kW-mo/yr
|
$7,938
-
MMBtu
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $3,948 | $14,095 | - | - |
$3,948
-
MMBtu
|
- | - | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $9,647 | $48,320 |
$125
3,061
kWh
|
$66
-
kW-mo/yr
|
$8,177
-
MMBtu
|
- | $1,280 | |
| 06 | 2.7135: Install occupancy sensors | $94 | $230 |
$94
2,302
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $79 | $324 |
$79
1,940
kWh
|
- | - | - | - | |
| 08 | 2.1321: Replace fossil fuel equipment with electrical equipment | $621 | $299 |
$(-43.4)
(-1,067)
kWh
|
- | - |
$664
-
MMBtu
|
- | |
| 09 | 2.6212: Turn off equipment during breaks, reduce operating time | $190 | $180 |
$190
4,662
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $28,961 | $73,135 |
$7,113
174,807
kWh
|
$(-158.2)
-
kW-mo/yr
|
$20,063
-
MMBtu
|
$664
-
MMBtu
|
$1,280 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs