ITAC Assessment: DS0085
ITAC logo
ITAC Assessment: DS0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Precast Concrete Products
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 212,800
ft2
Annual Production 58,500
ton
Production Hrs. Annual 7,488
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,121 2,398,007
kWh
Electricity Demand $50,510 7,180
kW-mo/yr
Electricity Fees $1,510 -
Natural Gas $132,384 43,990
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,965 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,519

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,039 $2,054 $705
21,395
kWh
$334
-
kW-mo/yr
- - - -
02 2.2135: Repair and eliminate steam leaks $16,781 $3,200 - - $16,781
-
MMBtu
- - -
03 2.2153: Close off unneeded steam lines $2,286 - - - $2,286
-
MMBtu
- - -
04 3.5313: Increase amount of waste recovered for resale $8,699 $880 - - - $8,699
-
lb
- -
05 3.5311: Recover and reuse waste material $6,837 $40,000 $(-694.0)
(-21,102)
kWh
$(-537.0)
-
kW-mo/yr
- $11,968
-
lb
$(-3,900.0) -
06 3.6192: Use a less expensive method of waste removal $20,475 $1,320 - - - $20,475
-
lb
- -
07 3.1175: Use a different or recycled raw material $62,848 $40,000 - - $12,148
-
MMBtu
- $343,200 $(-292,500.0)
TOTAL RECOMMENDED $118,965 $87,454 $11
293
kWh
$(-203.0)
-
kW-mo/yr
$31,215
-
MMBtu
$41,142
-
lb
$339,300 $(-292,500.0)
TOTAL IMPLEMENTED $26,519 $6,134 $705
21,395
kWh
$334
-
kW-mo/yr
$16,781
-
MMBtu
$8,699
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs