| Assessment Year | 1997 |
|---|---|
| Principal Product | Precast Concrete Products |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
212,800
ft2
|
| Annual Production | 58,500
ton
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $78,121 | 2,398,007 |
kWh
|
$0.033 |
| Electricity Demand | $50,510 | 7,180 |
kW-mo/yr
|
$7.03 |
| Electricity Fees | $1,510 | - |
|
- |
| Natural Gas | $132,384 | 43,990 |
MMBtu
|
$3.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $118,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,519 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,039 | $2,054 |
$705
21,395
kWh
|
$334
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2135: Repair and eliminate steam leaks | $16,781 | $3,200 | - | - |
$16,781
-
MMBtu
|
- | - | - | |
| 03 | 2.2153: Close off unneeded steam lines | $2,286 | - | - | - |
$2,286
-
MMBtu
|
- | - | - | |
| 04 | 3.5313: Increase amount of waste recovered for resale | $8,699 | $880 | - | - | - |
$8,699
-
lb
|
- | - | |
| 05 | 3.5311: Recover and reuse waste material | $6,837 | $40,000 |
$(-694.0)
(-21,102)
kWh
|
$(-537.0)
-
kW-mo/yr
|
- |
$11,968
-
lb
|
$(-3,900.0) | - | |
| 06 | 3.6192: Use a less expensive method of waste removal | $20,475 | $1,320 | - | - | - |
$20,475
-
lb
|
- | - | |
| 07 | 3.1175: Use a different or recycled raw material | $62,848 | $40,000 | - | - |
$12,148
-
MMBtu
|
- | $343,200 | $(-292,500.0) | |
| TOTAL RECOMMENDED | $118,965 | $87,454 |
$11
293
kWh
|
$(-203.0)
-
kW-mo/yr
|
$31,215
-
MMBtu
|
$41,142
-
lb
|
$339,300 | $(-292,500.0) | ||
| TOTAL IMPLEMENTED | $26,519 | $6,134 |
$705
21,395
kWh
|
$334
-
kW-mo/yr
|
$16,781
-
MMBtu
|
$8,699
-
lb
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs