ITAC Assessment: OK0326
ITAC logo
ITAC Assessment: OK0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product GAS COMPRESSOR ASSEMBLY
NAICS
n/a
SIC 3563: Air and Gas Compressors
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area
n/a
Annual Production 198
pieces
Production Hrs. Annual 8,500
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,674 2,537,515
kWh
Natural Gas $61,233 21,253
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,856 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,200

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2511: Insulate bare equipment $1,211 $1,382 - $1,211
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,545 - $1,715
47,479
kWh
- $(-170.0)
03 2.2437: Recover waste heat from equipment $518 $904 $(-27.0)
(-879)
kWh
$545
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $138 $85 $138
2,345
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $357 $150 $334
5,569
kWh
- $23
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $87 - $87
1,465
kWh
- -
TOTAL RECOMMENDED $3,856 $2,521 $2,247
55,979
kWh
$1,756
-
MMBtu
$(-147.0)
TOTAL IMPLEMENTED $3,200 $1,532 $2,136
54,513
kWh
$1,211
-
MMBtu
$(-147.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs