ITAC Assessment: BD0489
ITAC logo
ITAC Assessment: BD0489
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Recognition Signage, Donor Walls, Metal Etching
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 50,000
ft2
Annual Production 1
units
Production Hrs. Annual 2,080
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,685 519,840
kWh
Electricity Demand $33,319 2,758
kW-mo/yr
Electricity Fees $2,096 -
Natural Gas $9,088 1,461
MMBtu
LPG $1,101 17
MMBtu
Waste Disposal Costs
Water Usage $553 155
Tgal
Water Disposal $650 155
Tgal
TOTAL YEARLY COSTS $99,492
RECOMMENDED SAVINGS* $24,359 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,215 $16,983 $8,422
83,117
kWh
$5,793
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,863 $7,497 $3,471
34,257
kWh
$2,392
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $1,418 $825 $698
6,889
kWh
$720
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $1,075 $1,320 $637
6,285
kWh
$438
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $744 $411 $455
4,493
kWh
$83
-
kW-mo/yr
- $86 $120
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $578 $400 $343
3,382
kWh
$235
-
kW-mo/yr
- - -
07 2.2437: Recover waste heat from equipment $270 $800 - - $270
-
MMBtu
- -
08 2.4221: Install compressor air intakes in coolest locations $196 $400 $116
1,143
kWh
$80
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $24,359 $28,636 $14,142
139,566
kWh
$9,741
-
kW-mo/yr
$270
-
MMBtu
$86 $120
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs